A PQQ (pre-qualification questionnaire) is the first-stage questionnaire a buyer uses to check that suppliers are suitable before inviting them to tender. An ITT (invitation to tender) is the second stage: the full tender pack that shortlisted suppliers answer with their solution and price. Put simply, the PQQ decides who is allowed to bid and the ITT decides who wins the contract.
This guide explains what each document means, what buyers ask in them, how they have changed under the Procurement Act 2023, and how to get through both stages.
What does PQQ stand for?
PQQ stands for pre-qualification questionnaire. It is used in two-stage tenders, where a buyer expects a lot of interest and wants to shortlist suppliers before asking for full bids. The PQQ looks at your organisation rather than your solution: who you are, whether you are financially sound, whether any grounds for exclusion apply, and whether you have done similar work before.
You will also see the same stage called an SQ (selection questionnaire) or SSQ (standard selection questionnaire). The SQ was introduced to standardise PQQs across the public sector, but the purpose is identical. “PPQ” is a common misspelling of PQQ – it means the same thing.
What is a PQQ used for in procurement?
Buyers use a PQQ to remove suppliers who could not deliver the contract before anyone spends time writing or evaluating a full bid. Some questions are pass/fail (for example, holding the right insurance or not having relevant convictions); others are scored, usually your experience on comparable contracts. The highest-scoring suppliers are then invited to the next stage of the tender process.
Not every tender has a PQQ. In an open procedure, suitability and quality are assessed together in a single submission. If you are new to the different routes, see the main types of tender explained.
What does a PQQ ask?
Company information
Legal name, registration number, ownership, contact details and whether you are bidding alone, as a consortium or with subcontractors.
Grounds for exclusion
Declarations about criminal convictions, insolvency, tax and professional misconduct. These are pass/fail, so answer them accurately and explain any self-cleaning steps you have taken.
Financial standing
Accounts, turnover, cash flow and sometimes credit checks, plus evidence of insurance cover. Buyers want to know you can absorb the cost of delivering the contract. Our guide to the financial checks buyers actually run covers this in detail.
Technical and professional ability
Case studies or references from similar contracts, the size and skills of your team, and relevant accreditations. Depending on the sector this may include ISO 9001 or health and safety schemes such as CHAS, Constructionline or SafeContractor.
Policies: health and safety, environment, equality and social value
Most buyers ask for your policies and how you apply them in practice. Environmental commitments, equal opportunities and social value are now standard, particularly in public sector work.
PQQs under the Procurement Act 2023
Public procurements in England, Wales and Northern Ireland that started on or after 24 February 2025 follow the Procurement Act 2023. The Act does not use the term PQQ. Instead, buyers set conditions of participation to check a supplier’s legal and financial capacity or technical ability, and suppliers keep their core information (company details, financial information and exclusion declarations) on the government’s Central Digital Platform rather than re-entering it for every bid.
In practice, many buyers still run a first stage that shortlists suppliers, and most people in the industry still call it a PQQ or SQ. Procurements started before 24 February 2025 continue under the old rules, and Scotland has its own procurement regime – see tendering in Scotland. For a wider summary of the changes, read what the Procurement Act means for SMEs.
What is an ITT?
An ITT (invitation to tender) is the formal set of documents a buyer issues inviting suppliers to submit a bid for a contract. In a two-stage tender it follows a successful PQQ; in a single-stage tender it is the only stage. Where the PQQ asks whether you can do the job, the ITT asks exactly how you will do it and at what price.
ITTs are usually published through an e-tendering portal. Follow every instruction on format, word counts, page limits and file types – non-compliant submissions can be rejected without being scored.
What does an invitation to tender include?
Specification or scope of works
What the buyer needs: outputs, service levels, timescales and technical requirements. In construction this often includes surveys, drawings and programmes.
Instructions and deadline
How and when to submit, how to ask clarification questions, and the timetable through to contract award.
Award criteria and weightings
How bids will be scored, typically a split between quality and price. Read these carefully: they tell you where the marks are. Our guide to the most economically advantageous tender (MEAT) explains how quality and price are balanced.
Quality questions and method statements
Written answers on how you will deliver, manage risk, mobilise and add social value. These usually carry most of the quality score – see method statements in tenders.
Pricing schedule and contract terms
A pricing template or schedule of rates to complete, and the terms you will be signing up to. Our guide on how to price a public sector tender walks through it.
PQQ vs ITT: the key differences
| PQQ / SQ | ITT | |
|---|---|---|
| Stage | First stage (selection) | Second or only stage (award) |
| Question it answers | Is this supplier capable and eligible? | Which bid offers the best solution and value? |
| What you provide | Company details, exclusion declarations, finances, insurance, experience, accreditations | Method statements, quality answers, pricing |
| Outcome | A shortlist of suppliers | Contract award |
Tips for getting through the PQQ stage
- Keep a ready-to-use library of policies, accounts, insurance certificates and accreditations.
- Choose case studies that match the size, sector and complexity of the contract, and quantify the results.
- Answer exactly the question asked, using the buyer’s own wording and within the word limit.
- Check pass/fail requirements such as minimum turnover and insurance levels before you start.
- Ask a clarification question if anything is unclear – the answer is shared with all bidders, but it is better than guessing.
If you want a second pair of eyes before you submit, our bid review service checks compliance and scoring potential, and our bid writers can prepare your PQQ and ITT responses for you.
PQQ and ITT FAQs
Is a PQQ the same as a tender?
No. A PQQ is the selection stage that comes before the tender. Passing it gets you invited to tender; it does not win you the contract.
Is a PQQ the same as an SQ?
Yes, in purpose. The selection questionnaire (SQ) is a standardised version of the PQQ used in public sector procurement. Under the Procurement Act 2023 this stage is set out as conditions of participation.
What is the difference between an ITT and an ITQ?
An ITQ (invitation to quote) is a lighter request, usually for lower-value or simpler purchases, where price matters most. An ITT asks for a fuller response covering quality as well as price.
Do all tenders have a PQQ?
No. Single-stage (open) tenders assess suitability and quality in one submission, and call-offs from frameworks usually go straight to a mini-competition because suppliers were checked when the framework was set up.